Operations in sub-assemblies

Routing

Operations in sub-assemblies

Postby michael_aussie » Thu Jul 23, 2009 3:59 am

Hi,

We use multi-level Bill Of Materials. The sublevels are phantoms.
When you raise a Works Order in Sage for a BOM, the components in the phantoms are allocated to the WO.
However, if the phantom sublevels have routes with operations, they are not allocated to the WO. :?
Only the operations the the master BOM are allocated to the WO.

For practical reasons, we cannot put all the operations in the master BOM.
For practical reasons, we cannot raise WOs for the phantoms.
To get around this we currently don't use routes. All of our operations are stock-codes and are included in the BOMs.
Does anyone else have multilevel BOMs with operations?? :?: How do you handle this issue??? :?:

To use Preactor we need to set up routes and operations in the WOs.

Any suggestions??? :?:

Regards,
Michael.
michael_aussie
 
Posts: 45
Joined: Fri Oct 10, 2008 12:15 am
Location: Australia

Re: Operations in sub-assemblies

Postby michael_aussie » Wed Jul 29, 2009 12:31 pm

With no replies..... does this mean that no one uses operations in sub-assemblies??
michael_aussie
 
Posts: 45
Joined: Fri Oct 10, 2008 12:15 am
Location: Australia

Re: Operations in sub-assemblies

Postby michael_aussie » Wed Sep 16, 2009 4:10 am

Well some water has gone under the bridge .. and now I am a route guru!!!

Well not really, but I do now have a good understanding.

Any questions, feel free to ask me.

I still haven't learnt "issue to stage" - any suggestions???
michael_aussie
 
Posts: 45
Joined: Fri Oct 10, 2008 12:15 am
Location: Australia

Re: Operations in sub-assemblies

Postby or-8 » Thu Sep 17, 2009 3:32 pm

We do use phantom sub-levels in our BOMS but I am not involved with Works orders too much.

Although the routing operations are not on the WO for the upper level item the cost is rolled up when doing a Costed Bill of Material for the upper level.

If the WO was used as a 'route card' things wouldn't get manufactured at the sub-level -
Do you have too many levels/BOMs to consider making subs non-phantoms and having MRP raise the WO for them?
User avatar
or-8
 
Posts: 31
Joined: Fri Sep 05, 2008 11:07 am

Re: Operations in sub-assemblies

Postby michael_aussie » Mon Sep 28, 2009 1:27 pm

Our BOMs are multi-level (sometimes up to 6 or 7).
Many BOMs are generated as a one off combination pulling together subassemblies.
We have created some "standard" routes. When we raise a WO for a BOM we call up and closest relevant route. We then modify as required.
michael_aussie
 
Posts: 45
Joined: Fri Oct 10, 2008 12:15 am
Location: Australia