We use multi-level Bill Of Materials. The sublevels are phantoms.
When you raise a Works Order in Sage for a BOM, the components in the phantoms are allocated to the WO.
However, if the phantom sublevels have routes with operations, they are not allocated to the WO.
Only the operations the the master BOM are allocated to the WO.
For practical reasons, we cannot put all the operations in the master BOM.
For practical reasons, we cannot raise WOs for the phantoms.
To get around this we currently don't use routes. All of our operations are stock-codes and are included in the BOMs.
Does anyone else have multilevel BOMs with operations??
To use Preactor we need to set up routes and operations in the WOs.
Any suggestions???
Regards,
Michael.